6 min read · Smart factory

After installing a machine data collection system, the same thing often happens: the OEE from the system is lower than the figure the shift lead used to write in the report. Production says the system is wrong; the system team says the old report was loose. Usually neither is true.
The most common cause is that the two sides use different definitions. OEE (Overall Equipment Effectiveness) is the product of three values: availability, performance and quality. Compare them one at a time and you can see where the difference is. The example here is hypothetical.
Why compare part by part
Arguing over a single overall number does not help, because one OEE figure hides the differences inside it. If you break it into planned time, downtime, total pieces and good pieces, you can immediately see which side counts what differently, and fix exactly that.
This comparison does not decide which side is right. The goal is for everyone to use the same definition, and to write that definition into a document everyone can see.
Compare in this order
- Pick one shift and one machine where the numbers clearly differ. Use exactly the same time window for both sides.
- Compare planned production time: does each side deduct breaks, changeover time and planned maintenance?
- Compare downtime: how many minutes must a minor stop last before it is counted, and why are some stops not counted?
- Compare total pieces, from the machine counter versus from what people wrote down.
- Compare good pieces: are reworked pieces counted as good?
- Compare the ideal cycle time (reference rate): do both sides use the same value?
- Once the cause is known, write the definition into a single document, then configure the system and the forms to match it.
| What is compared | Question to ask | Who answers | Example of a difference found |
|---|---|---|---|
| Planned time | Are breaks and changeovers deducted? | Shift lead and production | One side deducts changeover time, the other does not |
| Downtime | Stops shorter than how many minutes are not counted? | Production and maintenance | The shift report skips short stops; the system counts them all |
| Total pieces | Machine counter or hand count? | Production and control technician | The counter also counts pieces that were later rejected |
| Good pieces | Are reworked pieces counted as good? | Quality | The system takes the value from the sorter; the old report was filled in at end of shift |
| Reference rate | Standard value or best demonstrated value? | Process engineer | The two sides use values from different years |
Common mistakes
- Adjusting the system's figures to equal the old report without asking what the old report counted.
- Comparing different time windows, for example the system's first shift is cut at 10:00 but the report is cut at 06:00.
- Not excluding periods when the system has no data and counting them as running time. See the article on data gaps.
- Keeping the definition in one person's head, so it differs again when that person changes.
Hypothetical example: morning shift on an assembly line
The system reports an OEE of 73.3% for the morning shift, but the shift report says 78.6%. Comparing part by part shows that total and good pieces match and the reference rate is the same. The only difference is planned time.
- Actual run time is 378 minutes, the same for both sides. Total pieces are 20,412 and good pieces are 19,800 (quality about 97.0%).
- The reference rate is 60 pieces per minute, so the expected output is 378 × 60 = 22,680 pieces. Performance is 20,412 ÷ 22,680 = 90.0%.
- The shift report uses planned time of 420 minutes (480 minus a 30-minute break and a 30-minute changeover). Availability is 378 ÷ 420 = 90.0%. OEE = 0.90 × 0.90 × 0.97, about 78.6%.
- The system uses planned time of 450 minutes (deducting only the 30-minute break). Availability is 378 ÷ 450 = 84.0%. OEE = 0.84 × 0.90 × 0.97, about 73.3%.
The two figures differ by about 5 percentage points, and neither side is mathematically wrong. The difference is whether the 30-minute changeover belongs in planned time or counts as downtime. The team has to agree on this and write it down. If it counts as downtime, the figure shows how much time changeovers really take.
Limitations and cautions
All numbers in the example, including times, piece counts and percentages, are hypothetical and do not come from a real plant. The right definition depends on the process and on how each site is managed; there is no single correct definition for every factory.
If OEE is reported to customers or auditors, agree the definition with the parties concerned first. A data collection system does not change the definition on its own; someone has to decide and record it.