7 min read · ERP and CRM

Many factories and workshops have two figures that do not agree. The first is the cost that is expected to apply; the second is the cost that actually occurred. The difference between them tells you where to look, if you know how to read it.
This article explains the difference between standard cost and actual cost, where variances come from, when to update the standards, and how to read the report. The examples are hypothetical.
What are standard cost and actual cost
- Standard cost is the unit cost set in advance. It is calculated from the bill of materials (BOM), the expected material prices, the working time per unit and the labour rate.
- Actual cost is the cost that really occurred in that production run, based on the materials used, the time spent and the prices actually paid.
A standard cost is not a number that is right or wrong; it is a yardstick. It is like the standard travel time for a route: if today took longer, you ask whether there was traffic, a breakdown, or slow driving.
Why you need both figures
With only actual cost, every time a material price moves the product cost moves with it, and you cannot tell whether cost rose because you bought at a higher price or because you used more material. Standard cost separates those two things, and lets you set selling prices or relieve cost during the month without waiting for the period to close.
Where variances come from
| Variance type | Meaning | Example causes | Who should look |
|---|---|---|---|
| Price | Material bought at a higher or lower price than standard | Market price rise, small-lot buying, freight | Purchasing |
| Usage | More or less material used than the recipe | Scrap, offcuts, over-measuring, an outdated recipe | Production, quality |
| Labour | Time or labour rate differs from standard | Machine stops, rework, overtime, new staff | Line supervisor, production |
| Yield | Fewer good units than expected from the material put in | Downgraded product, defective parts, unstable machine setup | Production, quality |
A variance where actual cost is above standard is called unfavourable; one where it is below standard is called favourable. Favourable variances should also be checked, because they may come from using material of lower quality than the recipe, or from incomplete recording of quantities.
How to set and use standard cost
- First check that the recipe and the production steps match what is actually done (see the separate article on the difference between a BOM and the production steps).
- Set the standard material prices from the latest purchase price or an average, according to company policy.
- Set the standard time per unit from actual time measurements or historical data, not from hopes.
- Set the labour rate and the production overhead absorbed per hour as defined by accounting.
- Let the system calculate the standard cost per unit, then use it to compare with the actual cost of each production order.
- Review the standards at a set interval, and record who changed what and when.
How often to update the standards
There is no single interval that suits everyone. The principle is to update when the standard stops being a reliable yardstick. If you update every time a price moves, the variances vanish and the report tells you nothing. If you never update, the variances are large every month and nobody pays attention.
| Event | What to do | Who decides |
|---|---|---|
| The scheduled review comes round (for example once a year or once a quarter) | Review the whole set of prices, times and labour rates | Cost accounting, together with production and purchasing |
| The recipe or production steps change | Set a new standard for that product immediately | Production, with cost accounting approving |
| Variances in the same direction repeat for several months | Check whether the standard is out of date or the process has a problem, then decide to fix one or the other | Production manager and accounting |
When you change a standard, you must also deal with remaining stock and work in progress that still carry the old price. How to post this part should be checked with your company's accountant.
How to read a variance report
- Look at the total first: is actual cost above or below standard, by how much, and what percentage is that?
- Split by type, price, usage, labour and yield, to see where most of the variance sits.
- Look at each product or production order and pick the top three with the largest variance.
- Ask the people involved what happened. The numbers only tell you where the difference is, not the cause.
- Record the cause and what will be fixed, then check in the next period whether the variance has fallen.
Hypothetical example
Produce 1,000 units. The standard per unit is 2 kilograms of material at 30 baht per kilogram, and 0.1 hours of labour at 200 baht per hour.
| Item | Standard | Actual | Variance (baht) |
|---|---|---|---|
| Material used | 2,000 kg | 2,100 kg | 100 kg over |
| Material price per kg | 30 baht | 31 baht | 1 baht higher |
| Total material cost | 60,000 | 65,100 | 5,100 (unfavourable) |
| Labour hours | 100 h | 110 h | 10 h over |
| Total labour cost (200 baht per hour) | 20,000 | 22,000 | 2,000 (unfavourable) |
| Material and labour combined | 80,000 | 87,100 | 7,100 |
The 5,100 baht material variance splits into two parts. The price variance is 1 baht higher multiplied by the 2,100 kilograms actually bought and used, which is 2,100 baht. The usage variance is 100 kilograms over multiplied by the standard price of 30 baht, which is 3,000 baht. Together, 2,100 + 3,000 = 5,100 baht, which matches the table.
The total variance of 7,100 baht is about 8.9 percent of 80,000 baht. Once split, you can see that 5,000 baht comes from using too much material (3,000) plus excess labour (2,000), while the higher purchase price accounts for 2,100 baht. So the problem is more about overuse than about buying at a higher price. The next place to look is why material was overused or wasted, such as scrap during production or frequent machine stops. The numbers point the way; they do not give the answer.
Common mistakes
- Setting the standard once and never reviewing it, so variances are high every month and nobody trusts the report.
- Adjusting the standard to the actual price every month, so the variances disappear and problems become invisible.
- A recipe in the system that does not match what is actually done, so the usage variance is high from day one.
- Not recording scrap or offcuts, so the usage variance does not reflect reality.
- Using variances to blame people, instead of finding where the process is abnormal.
Limits and cautions
A variance report is only as reliable as the source data: the recipe, material issues, labour hours and scrap recording. How production overhead is absorbed, how variances are posted in the accounts, and how stock is valued are accounting matters; check them with your company's accountant before setting anything up. All figures in this article are hypothetical examples and are not the costs of any business.